All projects

Li-ion cell — supplier comparison

High riskExpert reviewedVoltline Mobility · Cradle-to-gate · Scenario compare
Inventory Flow Editor - foreground LCI

Supplier B cell inventory

Edit NMC 811 baseline and Supplier B cell foreground flows, preserve source evidence, and keep reviewer notes tied to per 1 kwh cell capacity, cradle-to-gate.

Foreground flows
14
Supplier B evidence and process rows
Mapped rows
12
2 rows need attention
Mean DQI
8/10
Five pedigree sub-scores
Review coverage
12/14
2 open inventory tasks

Flow register

Select a row to inspect evidence, assumptions, and validation status.

FlowStageScenarioQuantityFactorStatusDQI
NMC 811 baselineScenario systemBaseline modelNMC 811 baseline1 functional unit62.00Mapped8/10
Supplier B cellCurrent scenarioActive modelSupplier B cell1 functional unit41.00Mapped8/10
Formation electricity factorAssumption parameterEnergy modelSupplier B cell0.34 kg/kWh3.70Mapped9/10
Cathode precursor emission factorAssumption parameterSupplier routeSupplier B cell7.8 kg/kg3.10Mapped8/10
Synthetic graphite shareAssumption parameterMaterial choiceSupplier B cell58 %2.10Mapped8/10
Solvent recovery rateAssumption parameterForeground processSupplier B cell91 %0.90Needs review5/10
Cell manufacturing yieldAssumption parameterForeground processSupplier B cell94 %1.00Mapped8/10
Cathode active materialForeground hotspotContribution modelAll scenarios370 index3.70Mapped8/10
Cell formation electricityProcess inputContribution modelAll scenarios240 index2.40Mapped9/10
Anode graphite productionProcess inputContribution modelAll scenarios160 index1.60Mapped7/10
Electrolyte and separatorProcess inputContribution modelAll scenarios120 index1.20Mapped8/10
Pack-ready logisticsProcess inputContribution modelAll scenarios110 index1.10Needs review5/10
Use renewable formation electricityScenario actionImprovement queueLow-carbon supply19 %1.90Mapped8/10
Switch to lower-carbon cathode precursorScenario actionImprovement queueLow-carbon supply14 %1.40Mapped7/10
Selected: NMC 811 baselineMappedAnalyst reviewed
14 of 14 foreground rows shown

Validation checks

Mapped

Baseline scenario is available for comparison.

Functional basis is attached to the project profile.

Audit notes

Local notes stay attached to the selected flow for review traceability.

Notes should be evidence-linked and suitable for report appendix review.
Battery LCA expertREVIEWER

Solvent recovery rate is the current inventory evidence focus. Keep its source, assumptions, and validation notes attached before report export.

Air-quality reviewerREVIEWER

Smog formation: VOC control evidence is pending for the selected supplier site. Evidence note: Solvent and transport emissions are represented with supplier defaults.